21 January 2015

Kitchen work

Work has started in what will be the new kitchen, plus some demolition in what was the original kitchen in the house.

Framing for new plasterboard on one wall and the ceiling is now up. These will be insulated, boarded then plastered. They should be done by the beginning of next week. It will take 10 weeks for the kitchen 'furniture' to arrive so the plan is have everything done; painting, tiling etc by the time that arrives.
At the far end of the house was the original kitchen with the remains of a cooking range. That has now been demolished, as has the shute to the right in the photo below. The shute was used for moving hay from the grenier (attic) to the manger on the cave (garage). Opening up the shute meant we had an easy way to get rid of all the rubble into the cave. This room will be an en-suite guest room … eventually.